Construction of the JEA H2.0® Purification Center began in 2023. Anticipated to be completed by late 2025, this state-of-the-art center will be located at 7599 Southside Blvd. in Jacksonville. More than just a typical facility, the H2.0® Purification Center demonstrates our commitment to sustainability and environmental stewardship. Follow us on this exciting journey as we pave the way toward a water-smart future for Northeast Florida.
Plaza Poured, Degas Installed, Driller Demob.
Bldg Enclosed, Awning Installed & Site Paved.
Lime system installed and road stabilized.
Exterior paint & replenishment well complete.
Begin exterior painting, HVAC installed.
Carbon vessels installed and pads poured.
Continue coating building exterior and drilling well.
Chemical storage structure is installed behind the building.
Building roof nearing completion and major equipment installed inside building.
Water tanks in top left constructed and aquifer replenishment well construction begins.
Building roof installation begins and well driller mobilizes on the top left corner of the site.
Construction of building walls and floors continue.
As walls are set the building concrete floors begin being set.
Exterior building walls are nearly complete.
Building walls and structural foundation take shape.
Visitor parking begins to take shape and stormwater pond is complete.
Chemical storage structure is installed behind the building.
Building foundation starts in the top left corner of the site.
Building foundation takes shape in the top left corner of the site.
Construction begins with site clearing and the beginning formation of the stormwater pond.