Laying the groundwork
Construction of the JEA H2.0® Purification Center began in 2023. Anticipated to be completed by spring 2026, this state-of-the-art center will be located at 7599 Southside Blvd. in Jacksonville. More than just a typical facility, the H2.0® Purification Center demonstrates our commitment to sustainability and environmental stewardship. Follow us on this exciting journey as we pave the way toward a water-smart future for Northeast Florida.
Latest Updates
December 2025
Landscaping Complete, System Testing.
November 2025
System recirculation, fencing installed.
October 2025
Exhibit training & Process Functional Testing.
September 2025
Landscaping installed and visitor center exhibits completed.
August 2025
Plaza Poured, Degas Installed, Driller Demob.
July 2025
Bldg Enclosed, Awning Installed & Site Paved.
June 2025
Lime system installed and road stabilized.
May 2025
Exterior paint & replenishment well complete.
April 2025
Begin exterior painting, HVAC installed.
March 2025
Carbon vessels installed and pads poured.
February 2025
Continue coating building exterior and drilling well.
January 2025
Chemical storage structure is installed behind the building.
December 2024
Building roof nearing completion and major equipment installed inside building.
November 2024
Water tanks in top left constructed and aquifer replenishment well construction begins.
October 2024
Building roof installation begins and well driller mobilizes on the top left corner of the site.
September 2024
Construction of building walls and floors continue.
August 2024
As walls are set the building concrete floors begin being set.
July 2024
Exterior building walls are nearly complete.
June 2024
Building walls and structural foundation take shape.
May 2024
Visitor parking begins to take shape and stormwater pond is complete.
April 2024
Chemical storage structure is installed behind the building.
March 2024
Building foundation starts in the top left corner of the site.
February 2024
Building foundation takes shape in the top left corner of the site.
January 2024
Construction begins with site clearing and the beginning formation of the stormwater pond.